New Delhi, November 29, 2026: Bharat Petroleum Corporation Limited (BPCL) has approved an estimated ₹1,26,656-crore investment for a greenfield refinery and petrochemical complex at Ramayapatnam in Andhra Pradesh. The company’s board cleared the project on November 28, with commercial operations targeted for July 2032.
The approval is a major long-term capacity decision, but it is not a construction-completion announcement. BPCL said the project remains subject to government, statutory and regulatory approvals, and the cost estimate carries a plus-or-minus 20 per cent variation.
What BPCL plans to build
The integrated complex is planned to include a 9-million-tonne-per-annum (MMTPA) crude oil refinery, a 1.5-MMTPA mixed-feed ethylene cracker and downstream petrochemical units. BPCL’s exchange filing gives a combined throughput of 10.5 MMTPA and an expected petrochemical intensity of about 34 per cent.
The project will be implemented through a wholly owned subsidiary of BPCL. The company says the configuration is designed to produce both transportation fuels and petrochemical feedstocks, rather than operating as a refinery alone.
How the project will be funded
The board has approved an equity infusion of up to ₹44,330 crore into the project subsidiary, to be made in one or more tranches. That figure includes an equity contribution of up to ₹4,900 crore approved earlier. The latest infusion is subject to approval from the Cabinet Committee on Economic Affairs and other applicable clearances.
BPCL said the overall project will use a combination of equity and debt, with financing arrangements with lenders still being finalised. The total project cost is estimated at ₹1,26,656 crore, with a stated variation of plus or minus 20 per cent.
Why BPCL says more capacity is needed
BPCL’s filing lists its existing refining capacity at 35.3 MMTPA and capacity utilisation at 116.6 per cent in FY 2025–26. The company says the Ramayapatnam complex is intended to address a widening gap in key transportation fuels and India’s growing petrochemical supply needs.
The company expects the integrated facility to improve domestic availability of petroleum products, reduce reliance on imports of selected polymers, improve value realisation from refinery-petrochemical integration and support downstream chemical and polymer industries. These are the project’s stated objectives; actual supply and import effects will depend on the facility being completed and operating as planned.
What the July 2032 target means
July 2032 is BPCL’s estimated scheduled commercial operation date. The project will therefore take several years to move from board approval through clearances, financing, construction and commissioning. The announcement does not change petrol or diesel prices and does not add fuel to the market immediately.
Sources and further reading
- BPCL’s November 28 stock-exchange filing
- The Economic Times: BPCL approves ₹1.26 lakh crore Andhra project
- Business Standard: BPCL clears Ramayapatnam refinery-petrochemical complex
Related Infoflick coverage: November foreign portfolio flows and the rupee and India’s latest inflation and growth indicators.
Image credit: Rehman Abubakr / Wikimedia Commons, CC BY-SA 4.0. The photograph shows BPCL’s Kochi Refinery for illustration; it is not the proposed Ramayapatnam facility. Licence: https://creativecommons.org/licenses/by-sa/4.0/